The Laramie Range Wind Project will minimize the potential effects on local roads by entering into a road maintenance agreement with Laramie County outlining the process of improving and repairing roads that will be used during construction and operations. Per the Laramie County regulations (LUR 2-2-125(c)(xiii)), Laramie Range Wind will:
(A) Submit a detail map of known haul routes with the wind energy permit application
(B) Complete a pre-construction baseline survey prepared by a mutually agreed upon professional engineer to determine existing road conditions
(C) Engage a third-party engineer to assess the potential for damage or impact to the roads detailed in the haul route.
(D) Finalize a mitigation plan and/or long-term road maintenance plan to address the impacts to the roads as determined in the assessment
(E) Obtain the third-party engineer’s estimate for the total estimated cost to improve, maintain or repair the existing roads as detailed in the mitigation/maintenance plan
(F) Put up financial assurance in the amount necessary to repair any damage to public roads as a result of project construction or operations
(G) Perform additional information, studies, or reports as reasonably determined by the Board as necessary
As a long-term community partner, the Laramie Range Wind Project will leave the roads in the same or better condition as prior to construction.